The audit trail for Gulf state capital: every announced megawatt, megatonne and megadeal tracked from press release to steel in the ground.3 September 2026
Maintained dataset · weekly

The Energisation Ledger

Every announced MENA data centre and IPP: announced capacity, financing status, EPC awarded, chip licence status, stated energisation quarter, slip to date in quarters.

35 active rowsVerified as at 3 September 2026 at 11:28 UTCEvery value links to its source
ProjectCountryLocationTypeDeveloperAnnounced capacity, MWOperational capacity, MWAnnouncedFinancing statusEPC awardedChip export licence, as reportedStated energisationCurrent recorded statusStatus as atSlip, quartersVerified as at
AWS and HUMAIN AI ZoneSaudi ArabiaRiyadhdata centreAWS and HUMAIN502026-08-31announced2026-09-023 September 2026
DataVolt Oxagon data centre campusSaudi ArabiaOxagon, NEOMdata centreDataVolt1,5002025-02-11under construction2026-08-313 September 2026
Obelisk solar and storageEgyptIPP solarScatec1,1001,1002025-06-15financial closeScatecoperational2026-08-133 September 2026
Jaalan Bani Bu Ali Wind IPPOmanAsh Sharqiyah South GovernorateIPP windEDF power solutions, Al Khadra Partners, OQ Alternative Energy1202025-12-16financial close2027-Q3financial close2026-08-11-43 September 2026
MEEZA M-Vault 6, 7 and 8 expansionQatardata centreMEEZA442025-08-27announcedannounced2026-08-063 September 2026
Bilaj Al Jazayer Solar IPPBahrainIPP solar1002025-10-202027-Q3announced2026-06-22-53 September 2026
Khazna QAJ1 AjmanUnited Arab EmiratesAjmandata centreKhazna Data Centers1002024-10-152025-Q3under construction2026-02-243 September 2026
Al Ajban Solar PVUnited Arab EmiratesAl Ajban, Abu DhabiIPP solarEDF Renewables, KOWEPO, Masdar1,5002024-04-29financial closePowerChina Huadong Engineering Corporation2026-Q3under construction2026-02-093 September 2026
NEOM Green Hydrogen ProjectSaudi ArabiaNEOMhydrogenNEOM Green Hydrogen Company (Air Products, ACWA Power, NEOM)3,9002020-07-07Air Productsunder construction2026-02-053 September 2026
Al Dhafra Solar PVUnited Arab EmiratesAbu DhabiIPP solarTAQA, Masdar, EDF, Jinko Power2,0002,0002020-07-26operational2026-01-193 September 2026
Khazna Solar PVUnited Arab EmiratesAl Khazna, Abu DhabiIPP solarENGIE and Masdar1,5002025-10-10financial closefinancial close2026-01-193 September 2026
Ibri III Solar and Storage IPPOmanAl Dhahirah GovernorateIPP solarMasdar-led consortium with Al Khadra Partners, KOMIPO and OQ Alternative Energy5002025-09-23financial close2027-Q1financial close2026-01-16-43 September 2026
AMEA Power Aswan solar and storageEgyptAswan GovernorateIPP solarAMEA Power and Kyuden International Corporation1,0002025-12-182026-Q2under construction2025-12-18-23 September 2026
Khazna Dammam data centre campusSaudi ArabiaDammamdata centreKhazna Data Centers2002025-12-16announced2025-12-163 September 2026
Microsoft and G42 200MW capacity expansion via KhaznaUnited Arab Emiratesdata centreKhazna Data Centers2002025-11-06announced2025-11-063 September 2026
Stargate UAEUnited Arab EmiratesAbu Dhabidata centreG42, OpenAI, Oracle, NVIDIA, Cisco, SoftBank1,0002025-05-222026-Q3under construction2025-10-163 September 2026
HUMAIN Dammam data centreSaudi ArabiaDammam, Eastern Provincedata centreHUMAIN1002025-08-262026-Q2under construction2025-08-263 September 2026
HUMAIN Riyadh data centreSaudi ArabiaRiyadhdata centreHUMAIN1002025-08-262026-Q2under construction2025-08-263 September 2026
Nairyah 1 IPPSaudi ArabiaEastern ProvinceIPP gasACWA Power, Saudi Electricity Company, KEPCO1,8002024-11-18financial closeSEPCO3 and Doosan Enerbility consortiumfinancial close2025-08-253 September 2026
Rumah 1 IPPSaudi ArabiaRiyadh ProvinceIPP gasACWA Power, Saudi Electricity Company, KEPCO1,8002024-11-18financial closeSEPCO3 and Doosan Enerbility consortiumfinancial close2025-08-253 September 2026
Al Kahfah Solar PVSaudi ArabiaHail regionIPP solarACWA Power and Badeel1,4251,4252023-05-22operational2025-08-213 September 2026
Ar Rass 2 Solar PVSaudi ArabiaAr Rass, Qassim ProvinceIPP solarACWA Power and Badeel2,0001,0002023-05-22partially operational2025-08-213 September 2026
Saad 2 Solar PVSaudi ArabiaRiyadhIPP solarACWA Power and Badeel1,1251,1252023-05-22operational2025-08-213 September 2026
Manah I Solar IPPOmanAl Dakhiliyah GovernorateIPP solarEDF Renewables and KOWEPO5005002023-03-23financial closeShanghai Electric2025-Q1operational2025-08-1823 September 2026
Noor Midelt IIMoroccoMideltIPP solarACWA Power4002025-08-06announced2025-08-063 September 2026
Noor Midelt IIIMoroccoMideltIPP solarACWA Power4002025-08-06announced2025-08-063 September 2026
MBR Solar Park Phase 6United Arab EmiratesMBR Solar Park, DubaiIPP solarDEWA and Masdar1,8008002023-09-07financial closepartially operational2025-06-103 September 2026
Amunet Wind Power PlantEgyptRas Ghareb, Red Sea GovernorateIPP windAMEA Power and Sumitomo Corporation5005002022-11-30operational2025-06-023 September 2026
Manah II Solar IPPOmanManahIPP solarSembcorp5005002023-03-19operational2025-05-043 September 2026
Khazna AUH4 and AUH8United Arab EmiratesMafraq and Masdar City, Abu Dhabidata centreKhazna Data Centers602025-04-21under construction2025-04-243 September 2026
Al Shuaibah 2 Solar PVSaudi ArabiaMakkah regionIPP solarACWA Power and Badeel2,0602,0602023-08-20CEEC JVoperational2025-02-203 September 2026
Abydos Solar PVEgyptAswan GovernorateIPP solarAMEA Power5005002022-11-30operational2024-12-163 September 2026
Al Shuaibah 1 Solar PVSaudi ArabiaAl Shuaibah, Makkah ProvinceIPP solarACWA Power6006002023-08-20CEEC JVoperational2024-11-133 September 2026
Ar Rass 1 Solar PVSaudi ArabiaIPP solarACWA Power, SPIC (Huanghe Hydropower Development), Badeel7007002022-03-08operational2024-08-153 September 2026
Sudair Solar PVSaudi ArabiaIPP solarACWA Power1,5001,5002021-08-16operational2024-01-033 September 2026

Rows for the United Arab Emirates and Saudi Arabia record dated data only: announced value, announced date, current recorded status and status date, each with its source. No derived field is computed for those rows.

Rows located in the United Arab Emirates and Saudi Arabia record announced and dated status data only, with no derived field. Chip export licence status is recorded only for rows outside those two countries. Financing and EPC fields are recorded only where a 2024 to 2026 source states them.

Provenance: each field records the value and the page that states it. Changes are versioned; see the method page for what verified-as-at means. Licence CC BY 4.0, attribution to Arabia Tomorrow.